JOC Non-Pre-Priced Work: Rules, Limits, and Audit Risk

8 min read · PreCon JOC

Every JOC task order is built on RS Means unit prices — hundreds of line items drawn from a published cost book, multiplied by a GC's coefficient. But sometimes the work needed simply does not appear in the book. Those items are called non-pre-priced work, or NPP, and handling them incorrectly is one of the fastest ways to generate an audit finding.

What non-pre-priced work actually means

The RS Means unit price book used by a JOC program contains thousands of line items covering most standard construction work. "Pre-priced" items are those that appear in the book — when both parties agree on quantity, the price is derived automatically: RS Means bare cost × city cost index × GC coefficient.

Non-pre-priced work is any item that cannot be reasonably matched to a line in the book. This includes:

Critical distinction

The GC's awarded coefficient does not apply to NPP work. NPP items are priced at their actual quoted cost — the coefficient adds no markup on top. This is why the NPP channel can be attractive to GCs who want to avoid coefficient pressure, and why agencies need strict NPP controls.

How NPP work is priced

Your solicitation should define the NPP pricing method explicitly. The standard approach is competitive quotes: the GC solicits at least two or three written quotes from subcontractors or suppliers and passes them to the agency for review. The agency approves the lowest responsive quote or negotiates before authorizing the item.

Some programs define a dollar threshold below which a single quote is acceptable and above which multiple are required. Common thresholds:

Item valueQuote requirement
Under $2,500Single written quote from the GC acceptable
$2,500 – $10,000Two competitive written quotes required
Above $10,000Three competitive written quotes; agency review required
Above $25,000Three quotes + independent cost review by agency

The exact thresholds vary by program — what matters is that they are defined in the solicitation, not established informally after the fact.

The NPP percentage cap — and why it matters

Every JOC program should define a maximum NPP percentage: the share of any task order's total value that may consist of non-pre-priced work. The purpose is to prevent the program from being used to circumvent the RS Means-based pricing that JOC was designed around.

Common caps range from 10% to 20% of a task order's total value. Some programs set both a task order cap and a program-wide cumulative cap. If neither is defined in your solicitation, there is effectively no control on how much of your JOC spend bypasses the coefficient entirely.

HIGH AUDIT RISK

Task orders where NPP exceeds the program's defined cap — or where no cap was defined — are a primary target in JOC audits. The auditor's question is simple: if most of this task order is NPP, why was it issued under the JOC contract instead of a separate competitive procurement?

Common NPP misuse patterns

HIGH

Pre-priceable items classified as NPP

A GC reclassifies an item that has a reasonable RS Means match as NPP in order to quote it at a higher rate without the coefficient applying. Auditors compare NPP line items against the RS Means book directly. If a pre-priced equivalent exists and was not used, the finding is that the agency overpaid.

HIGH

Sole-source quotes

The GC uses a subcontractor it controls or is affiliated with as the single quote source. Without genuine competition, the quote establishes whatever price the parties want. Agencies should require written certification that quotes are from arms-length parties and spot-check by soliciting an independent quote themselves.

MEDIUM

NPP used to absorb coefficient underrun

A GC wins a JOC contract with a low coefficient, then systematically routes profitable items through NPP to recover margin. If NPP as a percentage of total task order value consistently trends upward over the contract term, this pattern is worth investigating.

MEDIUM

NPP approved without written quotes on file

Agency approves NPP items verbally or based on the GC's cost summary, without retaining the underlying quotes. When auditors request the documentation, nothing is there. The finding is that the agency authorized payment without adequate price competition.

MEDIUM

NPP on straightforward routine work

Painting, standard electrical fixtures, basic HVAC components — items that have clear RS Means analogs — classified as NPP because the work is bundled with a specialty scope. Bundling is not a basis for NPP classification; each line item stands on its own.

What your solicitation must say about NPP

A defensible JOC program needs all of the following NPP provisions in the solicitation document:

01

Definition of NPP

Explicit criteria for what qualifies as non-pre-priced. 'Not in the RS Means book' is insufficient — most general construction is in the book. The standard is 'no reasonable match exists in the book after a good-faith search.'

02

Quote requirement by dollar tier

The number of quotes required at each dollar threshold, the form they must take (written, signed, on supplier letterhead), and who reviews them (agency project manager, procurement officer, or both).

03

NPP cap per task order

The maximum NPP percentage of any single task order's total value. Most programs set this at 10–15%. State the consequence of exceeding it (task order rejection, re-scoping required).

04

Agency approval requirement

NPP items above a threshold must be approved by the agency before the GC proceeds. Approval cannot be retroactive. The solicitation should name the authority level required (project manager vs. procurement officer vs. both).

05

Documentation retention

All NPP quotes — including those not selected — must be retained for the life of the contract plus the statutory retention period. The agency should retain copies independently, not rely on the GC's files.

06

Audit rights on NPP

The agency reserves the right to independently solicit quotes for any NPP item and reject the GC's proposed price if the independent market check shows the GC's quote is not competitive.

Reviewing a task order proposal for NPP red flags

When a GC submits a task order proposal, check these before approval: