How RS Means Works in JOC

7 min read · PreCon JOC

Every JOC program is built on a unit price book. In Texas and most of the US, that book is RS Means — a national construction cost database published by Gordian. When a GC submits a coefficient of 1.0823, they're saying they'll perform work at 8.23% above whatever RS Means says the work costs. Understanding how RS Means prices are structured is essential for procurement officers auditing bids and contractors pricing competitively.

What RS Means actually is

RS Means is a database of construction task costs, organized by CSI MasterFormat division. Each line item represents a specific unit of work — installing a linear foot of 2×6 framing, painting a square foot of drywall, running conduit per linear foot. The database covers tens of thousands of tasks and is updated annually.

Gordian (which acquired RS Means in 2016) licenses the data to agencies and software vendors. When an agency launches a JOC program, they select a specific edition of RS Means — typically the most recent annual edition — as the program's unit price book. That edition stays fixed for the life of the contract, usually one to three years.

The practical implication: a contractor submitting to a program in 2026 may still be priced off a 2024 or 2025 edition. When reviewing bids, procurement officers should know which edition governs, because RS Means costs change year to year — sometimes significantly for materials categories.

What "bare cost" means — and what it doesn't include

Every RS Means line item shows a bare cost — the national average cost of labor, material, and equipment to perform that specific task, with no overhead and no profit. This is the number JOC programs reference.

ComponentIncluded in bare costNot included
LaborCraft wage at national avgPrevailing wage premiums, Davis-Bacon
MaterialMaterial unit costSales tax (varies by state)
EquipmentEquipment ownership & operatingFuel escalation
Overhead—GC overhead (typically 15–20%)
Profit—GC profit (typically 5–10%)

This matters because a contractor's coefficient must cover everything bare cost leaves out — overhead, profit, taxes, bonds, and any wage escalations required by the agency. A coefficient of 1.08 on a prevailing wage project means very different margins than 1.08 on a standard labor rate project.

Procurement officers reviewing coefficient submissions should ask: given the prevailing wage requirements in this program, is a coefficient of X actually sufficient for a GC to cover their costs? A bid that is suspiciously low may be from a contractor who hasn't accounted for prevailing wage — or who plans to cut corners on labor.

City Cost Index: adjusting national costs to your market

RS Means bare costs are national averages. Construction costs in Austin are different from costs in El Paso, which are different from costs in Dallas. RS Means publishes a City Cost Index (CCI) — a multiplier for each major metro area that adjusts the national average to local market rates.

Example: Painting drywall, 1,000 SF

RS Means bare cost (national avg)$0.52 / SF
Austin CCI (labor component)0.71
Dallas CCI (labor component)0.68
Adjusted cost depends on program edition + CCIvaries

The CCI is broken into sub-indices for labor, materials, and equipment separately. For most JOC work, the labor CCI drives the adjustment — material costs are more similar across markets than labor rates.

Some agencies apply the CCI at the program level (all tasks adjusted by a single composite factor); others apply it line by line. When auditing an independent cost estimate, make sure the CCI being applied matches the program's actual location and the edition year being referenced.

How contractors use RS Means to build their coefficient

A contractor building a JOC coefficient is essentially answering: for this program's typical work mix, what multiplier do I need on top of bare cost to cover my actual costs and make a profit?

That calculation depends on:

What agencies should know about RS Means in bid reviews

When procurement reviews a task order proposal from a JOC contractor, the contractor is quoting line items from the program's RS Means edition, multiplied by their coefficient. An agency doing an independent cost estimate should pull the same line items from the same edition and apply the same CCI — not a different year or a different geographic adjustment.

Common audit pitfall

Using a different RS Means edition year than the program's UPB to build your independent estimate will produce a meaningless comparison. Even a one-year difference in the database can produce cost variances of 3–8% across labor-intensive tasks. Always confirm which edition governs the program before starting an audit.

Red flags in task order pricing that suggest a contractor isn't using RS Means correctly:

Non-pre-priced work: when RS Means doesn't have a line item

RS Means covers tens of thousands of tasks, but it doesn't cover everything. When a task order requires work that isn't in the program's UPB, that work is called non-pre-priced (NPP). The JOC program must specify how NPP work is handled — typically through F7, the seventh adjustment factor.

The F7 coefficient applies a different multiplier to NPP work. Because NPP work can't be benchmarked against RS Means, it carries more audit risk. Best practices:

Independent cost estimates

Run your own RS Means-based estimate

PreCon JOC's independent cost estimate tool calculates bare costs from RS Means 2025 national averages. Paste a task order scope and get a line-item estimate in seconds.

Try the cost estimator →